Rehabilitation of an industrial zone


Project description:
- Treatment of concentrated pollution points (hydrocarbons and chlorinated solvents);

- Retaining work (installation of a pile wall);

- Nuisance management (installation of a tent and an air treatment system);

- Pumping and treatment of downhole water;

- Earthworks, stockpiling, sorting, treatment (liming of soil and chemical oxidation of the excavation bottom), disposal or reuse as backfill of materials from the site.

Key figures :

- Earthworks of 2500m3;

- 1,500 T of non-inert excavated material disposed of;

- 2,200 T of materials reused on site;

- Installation of an 1,800m² tent;

- 700m3 of water pumped and treated on site.